Construction of the variant to the village of Calheta – 1st phase – tunnels + 2nd phase

Work owner
Secretaria Regional do Equipamento Social e Transportes - Governo Regional da Madeira
Location
Madeira
Type of work
Major Road Works
Year
2001 | 2003 | 2005

The project included the execution of 4 Tunnels (900 ms, 750 m, 290 m, 1020 m), 1 special engineering structure (200 m long and 110 m high), 2 common engineering structures (90 m and 60 m) and 6 overpasses and underpasses.